My Baseline Capture Does Not Match the Data on My Schedule

Written on . By Tracy Mah

The out-of-sync baseline is actually a common issue that you will run into once you get comfortable scheduling and start getting more experience using Oracle’s Primavera P6 software. This was actually one of the first problems I had tackled with a client’s schedule as well – it was daunting to say the least. The size […]

Read More

Posted in Global Change, Primavera, Project Management, Scheduling

Q&A: “Why doesn’t the [BL1 Start] column data match the [Start] column data when the Baseline is set to Current Project?”

Written on . By Tracy Mah

When the Baseline is set to “Current Project”, you might notice that activities with actual dates are not getting the right baseline. Here is the solution:= 1. Open Project Management Application, Click [Admin] menu, then select [Admin prreferences…]. 2. Click the [Earned Value] tab on the left side.  Notice the [Earned value calculation] section at […]

Read More

Posted in Global Change

Q&A: “I have an event code error when updating baselines in P6.0. Can you help?”

Written on . By Tracy Mah

Your problem: Can you please help us to resolve this issue. I have attached the print screen of the error we receive whenever we try to update baseline. (See attached figure below: Error Message – Event Code D8E0794D ) My Solution: 1. Open “My Computer” from Windows Start, open [C:\Program Files\Common Files\Primavera Common\Java] folder 2. […]

Read More

Posted in Global Change