Q&A: “How can I accommodate resources working different hours per day on the same activity?

Written on . By Tracy Mah

The Primavera P6 Project Manager software uses the Admin setting for hours/day, hours/week, hours/month, hours/year to convert all units and duration type fields from the internally stored hours to the user’s display format preference of hours, days, weeks, months, or years. Internally-stored hours are always stored as hours in the database.  In most cases, the […]